Phase One ~ 2007

Date Major Milestone Status
19 - Sep Hold 'Concert Meetings' for Matrix instructions ~ distribute Matrix Completed
28 - Sep Departmental 'Consolidated' Matrices developed and submitted for review and discussion Completed
15 - Oct Order POC Hardware Completed
12 - Nov Develop Result Analysis ~ Vendor/ERP Application Recommendation Document Completed
13 - Nov Invite selected vendors to participate Completed
26 - Nov POC 1 Completed
3 - Dec POC 2 In Progress
10 - Dec POC 3  
14 - Dec Make Go/No-Go ERP Application Decision (Was POC Efficacious?)  
20 - Dec Finalize ERP Application Decision ~ Required For Purchase Selection  
15 - Jan Debrief Senior Management  
20 - Jan Finalized Vendor Selected Document & Phase 2 (Implementation) Roadmap